New teak decks were
laid throughout the yacht on the bridge, sidewalks,
aft deck and foredeck using sikaflex to bond to
the decks. The furniture on the flybridge
was renewed using laminated marine ply and spray
painted. |
| The layout was changed to
accommodate a wetbar with BBQ, sink and fridge
plus a 3.8 M RIB Avon tender w/ centre console
lifted onboard with a new stainless steel electric
davit with 240 degree pivot angle. All the stainless
steel on the bridge was changed using 316 L stainless
and Italian style bases. A new stainless steel
hatch to the flybridge was installed. The latest
Bose remote control audio system ensured excellent
audio effect whilst underway. |
| An awlgrip paint system was used
for the hull and superstructure. Bulwarks were
fitted to the yacht and new 316 L stainless steel
railings. A 6" aft swim platform was made in cold
moulded timber with a teak grating inserted. New
Lexan glass windshields were fitted and the anchor
windlass overhauled. The aft deck overhang was
replaced as was all exterior lighting by Cantalupi.
New 316 L stainless steel hatches were fitted
and new fenders and blue braided rope supplied
to the yacht, ensuring every detail was catered
for the owner |
 |
Two new Fischer
Panda 25 KW generators were installed using
the latest soundproofing technology ensuring whisper
quiet noise emissions. All thru hulls were replaced
with ABS approved Mylar thru hulls and a central
seachest ensuring ease of maintenance and quick
back up in the event of sea intake blockage. |
| A new hydraulic Naid bow thruster
& fin actuators / stabilisers were installed pump
driven from the generator. 316 L stainless steel
pipework was used throughout for this installation
from bow to mid ships to engine room. The air-conditioning
plant was overhauled and most compressors replaced
and the air handlers underwent major overhaul.
The main engines required a top end overhaul.
|
| |
The electrical system
was converted from 220 V 50 HZ to a dual; voltage
system and dual frequency. A new control panel
was installed and the yacht rewired approiatly
to meet highest standards. |